Author Topic: How to flag a WU so it will not be interrupted & bumped into the waiting queue?  (Read 21 times)

0 Members and 1 Guest are viewing this topic.

Offline archeye

  • Jr. Member
  • **
  • Posts: 13
    • View Profile
My example for this is the WU's from climateprediction.net. Specifically sub project Weather at Home 2 (wah2)".

The deadline for these tasks is over 330 days. The runtime on my computer is shown at about 12 days and I have 2 of these WU's with 3 days each runtime left.

Both these tasks have been bumped into Waiting to Run. Without manually suspending other project work to free up 2 CPU cores is there a way to either set them into a state where they run and do not get bumped into the waiting queue.

I was thinking to be able to somehow flag them as "High Priority" but maybe you have other thoughts.

I did look at the rules setting but could not see anything there that seemed like it would do what I am asking.

Offline fred

  • Global Moderator
  • Hero Member
  • *****
  • Posts: 3366
  • eFMer
    • View Profile
    • Trails
I did look at the rules setting but could not see anything there that seemed like it would do what I am asking.
BOINC handles this automatically a task with such deadline that far away will probably be bumped to the end of the list.
Not much you can do, but hope BOINC works as it should.

Offline archeye

  • Jr. Member
  • **
  • Posts: 13
    • View Profile
Thanks for the reply Fred. I guessed as much but just wondered if I was missing something.

I will just manually manage some CPU load balancing to get these WUs running again.