BT 0.91

Started by jjwhalen, November 29, 2010, 01:46:48 PM

Previous topic - Next topic

0 Members and 2 Guests are viewing this topic.

Pepo

Quote from: fred on November 30, 2010, 01:30:47 PM
Quote from: Pepo on November 29, 2010, 10:38:08 PM
No matter how many tasks are selected, the Task properties dialog always looks like this (we've lost Copy&Paste :( from the dialogs) - the most of lines are replaced by a single 'x' character:
The Project properties dialog looks fine.
I added a context menu to copy everything.
But whatever I try I can't reproduce the problems you have with the Task properties.
The columns are wide enough?

A screen-shot may tell it all.
Weird - it happens just with Slovak language - not with other ones ???



Columns are wide enough and the translations do exist for these lines - should have no influence on the values at the right side.
Peter

fred

Quote from: Pepo on November 30, 2010, 02:03:01 PM
Columns are wide enough and the translations do exist for these lines - should have no influence on the values at the right side.
I see it on my computer, with 0.92 it's gone, probably has something to do with the sorting flag, that was still enabled. ???
What I'm up to the other half of the time "BorregoWildflowers.org"